29.  VED analysis based on consumption of material.    FALSE

          30.  ABC analysis is based on importance of material.                 FALSE
          31.  The stocking limit  of A category items should not be more than 3 months.              TRUE
          32.  Unused store for 24 months is called surplus store.  TRUE

          33.  Single tender is given to more than one firm.             FALSE
          34.  Global tender is issued by Railway  Board.  TRUE
          35.  The amount of EMD may be converted into SD.   TRUE

          36.  It is not necessary to implement  Sudhir Chandra Report for tenders costing Rs. 50
                 Lakhs.              FALSE
          37.  SD and PG are obtained at the rate of 5% of tender cost.                 FALSE

          38.  There is 2 Member tender committee for tenders costing less than 20 lakhs.  TRUE
          39.  PAC certificate is signed by SAG grade officer for amount more than 3 lakhs.
                       TRUE

          40.  Scrap and unused store is not returned on DS-8.                  FALSE.














                                             Short Notes : MRT 1 & 2


           Q 1 & 12. Classification of HOER
           A) Intensive:  Work  which  is  hard  and  tiresome,  continuous  concentration  during  work,
           very  difficult  to  have  1  hours  rest time in a 8 hour shift come under Intensive category.
           Eg: Section Controller, Wireless Operator, Telephone Operator, etc.

           B)  Essentially Intermittent: Light job, 6 hours or more rest in a 12 hour shift come under
           Essentially  Intermittent  category.  Eg.,  Bearer  of  waiting  hall,  Gateman  (C  Class),
           safaiwalla,  etc.

           C)  Excluded:  Duty  timing  is  not  fixed.  24  hours  duty  not  included  in  HOER.  Eg.
           Supervisor, matron, workers in confidential work, Protection Force, etc.
           D) Continuous: Continuous working. Eg. Driver, Guard, TTE, Shunter, Clerk, Typist and

           other non classified categories.

           Q 2. PNM (Long-5 & Short)

        This mode of communication is done in three stages:
                   1.  At Railway’s level
                          1.  Division  / workshop
                          2.  Railway  / Zonal HQ
                   2.  At Railway  Board Level