Progress Calls : Leading to GO-Live!









            12       Initial Meeting #1: Objective: Introduction to On-property POC  XX/XX/2017
           weeks     Implementation Specialist will introduce themselves to the POC and discuss
                     ways of working and sign/review NDA


             11     Progress Call #2: Objective: Technical Readiness Checkpoint
           weeks    Implementation Specialist explains technical requirements for GRS to POC  XX/XX/2017
                                                                                                Details of
                                                                                                 each of
                                                                                                  these
            10      Progress Call #3: Objective: BETA Playbook              XX/XX/2017          contacts
           weeks    Implementation Specialist reviews toolkit with POC & assesses hotel’s
                    progress to completion                                                       (behind
                                                                                                each box)
                                                                                                 will be
             8      Progress Call #4: Objective: Check Data Clean-Up        XX/XX/2017         created and
           weeks    Check status of data clean-up & reviews 12 Week Prep Report                 added to
                                                                                                playbook
             7      Progress Call #5: Objective: Weekly Update              XX/XX/2017
           weeks    Discuss Training and any pre-work, as well as progress of Data Clean-up


           4 weeks  Progress Call #6: Objective: Training Readiness         XX/XX/2017
                    Confirm all personnel are ready confirm date, time and list of personnel



                    Progress Call #7: Objective: Pre-Prep/ Prep Procedures
           3 weeks  Verification with hotel and system check that Data Clean-up is done;   XX/XX/2017
                    Implementation Specialist gives go-ahead for Prep to begin



                    Progress Call #8: Objective: Prep & Readiness Review
           11 days  Implementation Specialist provides status of migration & sets expectations to   XX/XX/2017
                    POC


                    Progress Call #9: Objective: Final Readiness Review
           4 days   Implementation Specialist to explain cutover process & scheduling and confirm   XX/XX/2017
                    Cutover outage












    © 2016 IHG                                                                                           17
                             R  Restricted information intended for IHG colleagues, NOT external vendors
   12   13   14   15   16   17   18   19   20   21   22