Page 10 - B8773-AEW-XX-XX-PP-A-0001_[P8]_Contractors Manual
P. 10

1.1 Overview




       •  Domino’s preference is for a double glazed,        •  Aluminium  shop  fronts  are  to  be  polyester
          aluminium shopfront,  powder  coated  to               powder  coat  finished  to  colour  RAL  7043
          Traffic Grey RAL 7043.                                 Traffic Grey, and incorporate an aluminium
       •  All  window  frames,  stallrisers, and  fascia         entrance door fitted with full length handles
          board to be finished in RAL 7043 Traffic Grey.         to both sides, heavy duty letter box including
       •  Hand  painting  of  existing,  incorrectly             draft  flap/seals,  and  suitable  lock.  For  lock
          coloured,  aluminium  shopfronts  is  NOT              details  refer  to  Ironmongery  schedule.  The
          acceptable.                                            door  handles  are  to  be  finished  in  a  white
       •  Spray  painting  of  an  existing  aluminium           plastic material RAL 9010 to provide a ‘warm’
          shopfront  on site, even by a professional             surface as required by Part M.
          company, is NOT recommended.                       •  Contractor    must    ensure    that    aluminium
       •  Timber shopfronts   should always be repaired          sections    specified    for    door    frame    and
          as necessary and properly prepared before              door construction are sized to accept
          being primed, undercoated and two coats                specified  lock  components.  Especially  a
          of gloss paint applied in RAL 7043 Traffic Grey        75mm headrail on the drivers door.
       •  All  shop  front  works  are  subject  to  design   •  Where  masonry or concrete  rendered
          approved  by  DPG  and  will  have  formed             surfaces  require  painting,  refer  to  DPG
          part of the approved planning consent for              Property  Dept  for  further  guidance  if
          the store for appearance and materials of              necessary.
          construction.                                      •  A  powered  door  operating  mechanism
       •  All  works  by  contractor  must  comply  with         to  comply  with  ADM/Disabled  Regs,  is  not
          the  relevant  planning  consent (obtained             normally  required.  However,  if  it  is,  it  will
          by others).                                            be supplied and installed by a specialist
       •  The  Principal  Contractor  is  to  be  responsible    company.  It  will  require  a  13A  fused  spur
          for  all  works  associated  with  removal  and        above  the  ceiling  above  the  door.  It  will
          disposal of existing shop fronts, preparation          also  require  a  flat  panel  approx  150mm
          of  structural  opening  to  receive  new  shop        high at the head of the door to mount it on.
          front,  and  design,  supply  and  installation        This  will  be  visible  through  any  top  light  on
          of new shop front. The design should utilise           the doorframe and must be appropriately
          aluminium or timber sections, of appropriate           finished on both sides if visible from outside.
          size and lengths such that it is sound and fit     •  All glazing to new shopfronts and doors must
          for its purpose.                                       be  installed  in  compliance  with  regulation
       •  All  works  must  comply  with  appropriate            14 - glass safety legislation, of the Workplace
          Building  Regulations, and  in  particular Part        (Health,  Safety  and  Welfare)  Regulations
          M Access to and Use of Buildings, and Part K           1992.
          Protection from falling, collision and impact.     •  All  shopfront  entrances  must  be  designed
       •  In  the  rare  instance  where  an  automated          to  have  level  thresholds  unless  an  existing
          customer  entrance  door  is to  be installed,         stepped  access  arrangement  has  to  be
          the appropriate break out system or link               retained.  Where  a stepped access is
          to  the  fire  alarm  as  agreed  with  the  DPG       retained,  building  control  approval  for  the
          building  control  approved  inspector,  must          arrangement must be obtained.
          be installed accordingly.
       1.1                         Shopfronts - Overview                                 3 September 2018