4.4 Gas




          4.4.1 Gas Installation
          •  The  gas  installation  shall  commence  at        •  The ventilation control panel supplier will also
             the  outlet  of  the  gas  meter  in  the  position    provide a suitable 42mm gas solenoid valve
             indicated on the drawing.                              for installation, in the oven supply pipe, by
                                                                    the  main  contractor’s  Gas  Safe  registered
          •  Gas pipework shall be light gauge copper               (commercial classification) engineer.
             tube, to BS EN 1057 (1996), and shall be sized
             to carry the load of all ovens and gas fired       •  It is the main contractor’s  responsibility  to
             water heater operating simultaneously.                 ensure that the gas pipe is purged through
                                                                    the  valve  before  hand-over  of  the  system.
          •  The main pipe run to the ovens must always             If this is not done and the oven installers are
             be run in 42mm pipe.                                   unable  to  complete  their  commissioning,

          •  The  gas  supply  to  all  ovens  shall  be            any subsequent call backs will be charged
             terminated at outlets / branches to suit the           to the main contractor.
             oven manufacturers requirements.                   •  In  all  cases,  the  final  “Quick  Disconnect”

          •  As  far  as  possible  the  gas  supply  shall  be     gas  hoses  and  fittings  will  be  supplied
             concealed from public view.                            and  installed  by  the  oven  commissioning
                                                                    engineer.
          •  Lever  type  stop-cocks  shall  be  provided  in
             such a position that they are easily accessible    •  Testing and commissioning certificates must
             and would enable the gas supply to be cut              be provided by the Principal Contractor on
             off  quickly  in  the  case  of  an  emergency.        project handover.
             They should not be located at the “back” of
             ovens where access is difficult. The handles
             should be yellow ochre in colour.
          •  All pipework  shall be suitably primed and
             painted yellow ochre.

          •  Note  that  the  position  and  number  of  the
             gas connections will vary between different
             oven manufacturers.
          •  The  Gas  Safe  registered  (commercial
             classification)  engineer  MUST  check  if  they
             are unsure which is required. No claims for
             subsequent alteration will be accepted.










          4.4.1                      Gas Installation                                       3 September 2018