Page 74 - B8773-AEW-XX-XX-PP-A-0001_[P8]_Contractors Manual
P. 74
4.3.2 Electrical Services
• All electrical contractors employed on ANY • All wiring and cable containment shall be
Domino’s site, whether self-build or DP UK&I concealed within the building fabric and
Ltd build, MUST be NICEIC certified. within the false ceiling void.
• The project includes all of the Electrical • All wiring must be run in suitable conduits or
Services work associated with the fitting out cable trays.
of an existing unit to create a fully operational • Final locations of all outlets and equipment
Domino’s pizza delivery store. shall be in accordance with the DGP
• The Electrical Contractor shall be responsible Standard layouts and fully coordinated
for detailed design, supply, installation, co- with other trades. Any deviations from the
ordination with other disciplines, testing and standard details must be agreed with the
commissioning for all items as detailed in this Project Manager/Client prior to installation.
specification and accompanying drawings. • All wiring, including computer, telecoms
• Existing and new stores: contractor must and electrical, within the counter, shall be
provide isolator before board and meter. run in suitable trunking terminated through
• All works shall be carried out in accordance standard boxes. It is the responsibility of
with the latest relevant British and European the Main Contractor to ensure that this
Standards including BS7671 (18th Ed IEE is complied with by his electrical sub-
Wiring Regulations or subsequent updates/ contractor.
revisions), current at the time of installation. • Data and telecoms cables must each
emerge from walls/trunking in suitable back
The works shall include: boxes and be positioned so that standard
• Removal and disposal of any existing modular face plates may be fitted.
redundant installations. • Earth bonding of fixed metal equipment
• Mains distribution equipment. shall be carried out by the site electrician
• General lighting. as required by the Regulations.
• Emergency lighting. • Installation of RCBO’s is expected where
• External lighting. “Best Practice” would call for their use,
• Small power. even in discretionary or ‘grey areas’ of the
• Fixed power to equipment and signage. regulations.
• Computer cabling. • Final circuit testing MUST be in full compliance
• Fire Alarm. with the appropriate regulations.
• Telephone wiring. • O&M manual, testing and commissioning
• Door bell. certificates must be provided upon
• Testing and commissioning. completion of a project.
• Provision of record documentation.
• User/Client demonstration and training.
4.3.2 Electrical Services 30 May 2018