be  made  by  the  site  plumber  but  the  HVAC A F T


          4.6.4 Fresh Air Heating
          Type 1: Hot water powered system                      not done and the heater circuit freezes during
          It  is  Domino’s  standard  practice  to  fit  a  low   cold weather, the repair costs will be passed to
          pressure hot water (LPHW) heater battery in the       the Main Contractor.
          fresh air intake duct, to temper the intake air in
          cold weather conditions. (This is not intended to     Type 2: Electric powered fresh air heating system
          provide a guaranteed ambient, nor minimum,            Occasionally it may not be possible to provide
          temperature within the store).                        a  LPHW  system,  in  which  case  an  equivalent
                                                                electrically powered  heater  battery  will be
          The hot  water  will be  provided  by the  central    required  instead.  The  final  connections  will  be
          heating  circuit  of  a  gas  fired  condensing       made by the site electrician, but the  liaison
          combi-boiler installed as part of the shopfitting     noted above with the plumber, will in this case
                            D R
          contract. This boiler will provide approximately      be liaison with the electrician. This will require a
          18kW of heat, and the HVAC contractor should          suitable sized 3-phase electrical supply.
          supply and install a heater battery to this rating.

          The  final  water  plumbing  connections  will


          contractor  should  supply  a  suitable  3-way
          valve  and thermostat,  to control  the system
          according to the air temperature in the duct.
          It is NOT acceptable to rely solely on the boiler
          thermostat  to  switch  the  heating  circuit.  The
          HVAC  contractor  must  liaise  with  the  plumber
          to ensure the system is left working and provide
          any instructions that may be necessary to.

          The  plumber  should  install  suitable  isolating
          valves  on  both  sides  of  the  LPHW  coil  unit  to
          allow for  maintenance  and  removal    without
          affecting the rest of the installation. The heater
          circuit  MUST  be  filled  with  a  suitable  and
          approved  anti-freeze  fluid  on  commissioning.
          (“Suitable”  meaning  approved  by  the  boiler
          manufacturer for use in the make and model of
          boiler installed in each job)

          A label must be affixed inside the casing of each
          boiler, warning that the heating system contains
          anti-freeze  and  that  it  must  be  refilled.If  this  is