TotalAlert Infinity™ NFPA Medical Gas Notification System
2.0 Installation Procedures Alarm rough-in box must have rigid verti-
cal members for support on both left and
2.1 Alarm Panel Rough-In Box right sides. Power to alarm panel shall en-
ter through bottom left or top left conduit
The rough-in box can be installed between hole in rough-in box.
16” on center standard studs. Mounting 2. Remove cardboard dust cover and DISS
ears on either side of the rough-in box are tube assemblies (if included) and insert
provided for attachment to studs, with depth alarm rough-in box into wall opening.
adjustment to accommodate different thick- Secure with fasteners suitable for vertical
nesses of wall board. supports (Figure 18).
Knock out plugs are provided in the top 3. Mounting brackets on each side of rough-
and bottom of the box for routing of supply in box are adjustable and factory preset
power, Ethernet CAT5 cable, gas sensor tubes for 5/8” thick drywall. After drywall instal-
or other necessary wiring. lation, front edge of rough-in box should
DO NOT drill rough-in box. be flush with finished surface of wall. If
1. Prepare rough wall opening large enough needed, make any necessary bracket ad-
to accommodate alarm rough-in box. justments at this time (Figure 18).
4. Reinstall cardboard dust cover to prevent
dust and debris from entering the rough-
in box.
13.50”
10”
4”
Figure 17: Alarm Panel Rough-In Box Dimensions
Loosen nuts to adjust
rough-in box depth
(same each side)
Figure 18: Mounting Bracket Adjustment