Page 42 - Mercy College_BarrandBarr_7.26.17
P. 42
Mercy College DD Estimate
Victory Hall Addition / Renovation 07/26/17
Dobbs Ferry, New York
ESTIMATE DETAIL
LINE CODE ELEMENT DESCRIPTION QUANTITY UNIT UNIT RATE TOTAL
598 EPDM Membrane 1,152 SF $6.00 $6,912
599 Cover Board 1,152 SF $3.00 $3,456
600 Parapet Caps 26 LF $65.00 $1,690
601 Roof Edge 190 LF $65.00 $12,350
602 Rigid Insulation including low roof and elevator roof 1,152 SF $3.25 $3,744
603 Upcharge for tapered insulation; 1/8" 1,152 SF $2.75 $3,168
604 Flashings / termination to parapet/curb & main building 26 LF $5.00 $130
605 Temp protection 1,152 SF $4.00 $4,608
606 Studio Connector
607 EPDM Membrane 1,720 SF $6.00 $10,320
608 EPDM Roof Vertical Parapet 138 SF $6.00 $828
609 Cover Board 1,720 SF $3.00 $5,160
610 Parapet Caps 206 LF $65.00 $13,390
611 Integral Gutter 155 LF $65.00 $10,075
612 Rigid Insulation @ low roof and elevator roof 1,720 SF $3.25 $5,590
613 Upcharge for tapered insulation; 1/8" 1,720 SF $2.75 $4,730
614 Flashings / termination to parapet/curb & main building 155 LF $5.00 $775
615 Temp protection 1,720 SF $4.00 $6,880
616 Gym Roof
617 TPO Roof 18,182 SF $7.00 $127,274
618 TPO Roof Vertical Parapet 384 SF $7.00 $2,688
619 Cover Board 18,182 SF $3.00 $54,546
620 Parapet Caps 256 LF $60.00 $15,360
621 Rigid Insulation @ low roof and elevator roof 18,182 SF $3.00 $54,546
622 Upcharge for tapered insulation; 1/8" 18,182 SF $1.75 $31,819
623 Flashings / termination to parapet/curb & main building 540 LF $5.00 $2,700
624 Temp protection 18,182 SF $4.00 $72,728
625 Fastening plate & sealants at roof drains & overflow drains 14 EA $750.00 $10,500
626 Industry / Market Conditions Discount 1 LS -$85,000.00 -$85,000
627 73000 Roofing $380,967
628
629 74243 Metal Wall Panels
630 07 4243 Composite Metal Panels
631 Metal Panels
632 West Entrance
633 Alucobond 624 SF $60.00 $37,440
634 Studio Connector
635 Alucobond 96 SF $60.00 $5,760
636 Gymnasium
637 Alucobond 2,208 SF $60.00 $132,480
638 MCP1 1,171 SF $60.00 $70,260
639 Mechanical Screen A201 (Extent is unknown) 160 SF $50.00 $8,000
640 General
641 Misc articulations, detailing, flashing & trim pieces Included
642 74243 Metal Wall Panels $253,940
643
644 78000 Fireproofing
645 Fireproofing
646 Cementitious spray fireproofing to structural steel members 19,979 SF $2.50 $49,948
647 Fireproof patching Included
648 Miscellaneous
649 Non-trade, non-system firestopping 19,979 SF $0.10 $1,998
650 78000 Fireproofing $51,945
651
652 81000 Doors, Frames, & Hardware
653 Hollow Metal Door Frames (furnish)
654 HM frames 3'-0 x 7'-0 9 EA $185.00 $1,665
655 HM frames 6'-0 x 7'-0 1 EA $250.00 $250
656 Hollow Metal Doors (furnish)
657 HM insulated exterior doors, 3'-0 x 7'-0 11 EA $500.00 $5,500
14 of 27