Mercy College                                                                                                 DD Estimate
 Victory Hall Addition / Renovation                                                                              07/26/17
 Dobbs Ferry, New York
                                                    ESTIMATE DETAIL
   LINE     CODE                       ELEMENT DESCRIPTION                QUANTITY    UNIT  UNIT RATE      TOTAL


       954          Start up and testing                                           1   LS       $5,000.00        $5,000
       955          Warranty and closeout                                          1   LS       $5,000.00        $5,000
                    Industry / Market Conditions Discount                                                      -$75,000
       957  220000  Plumbing                                                                                   $382,950
       958
       959  230000  HVAC
       960          Equipment
       961           RTU 1                                                         1   ea      $10,000.00       $10,000
       962           ERU 1,2                                                       2   ea      $20,000.00       $40,000
       963           AC (VRV) w/ CU                                               25   ea       $7,000.00      $175,000
       964           ECUH                                                          1   LS       $4,000.00        $4,000
       965           EBB                                                           1   LS       $3,000.00        $3,000
       966           VAV                                                           3   ea       $2,000.00        $6,000
       967           Appurtenances (CUH's, EUHC's, DHC's, FTR)                     1   LS      $15,000.00       $15,000
       968          BMS                                                          150   ea       $1,400.00      $210,000
       969          Sheet Metal                                                25,000  lbs        $16.00       $400,000
       970          Heating HW piping                                           1,400  ft         $55.00        $77,000
       971          Refrigerant piping                                          3,200  ft         $60.00       $192,000
       972          RGD's                                                          1   LS      $25,000.00       $25,000
       973          Insulation (piping)                                         4,600  ft         $12.00        $55,200
       974          Coordination                                                   1   LS      $25,000.00       $25,000
       975          Test & Balance                                                 1   LS      $25,000.00       $25,000
       976          Start up and testing                                           1   LS       $5,000.00        $5,000
       977          Warranty and closeout                                          1   LS       $5,000.00        $5,000
       978          Industry / Market Conditions Discount                          1   LS      -$80,000.00     -$80,000
       979  230000  HVAC                                                                                      $1,192,200
       980
       981  260000  Electrical
       982          Demolition                                                   160   hrs       $140.00        $22,400
       983          New Distribution Panel Boards                                  2   ea       $7,500.00       $15,000
       984          New ATS-1                                                      1   ea      $15,000.00       $15,000
       985          Lighting Package & Controls                                20,000  sq ft      $12.50       $250,000
       986          Grounding                                                      1   LS      $12,500.00       $12,500
       987          Power outlets - including wiring back to panels              125   ea        $450.00        $56,250
       988          Power to equipment - including wiring back to panels          45   ea       $2,000.00       $90,000
       989          Fire Alarm (connect to existing)                              35   ea       $4,000.00      $140,000
       990          Coordination                                                   1   ea      $10,000.00       $10,000
       991          Start up and testing                                           1   ea       $5,000.00        $5,000
       992          Warranty and closeout                                          1   ea       $5,000.00        $5,000
       993          Industry / Market Conditions Discount                          1   LS     -$180,000.00    -$180,000
       994  260000  Electrical                                                                                 $441,150
       995
       996  310000  Excavation, Sitework & Utilities
       997          Site Demolition & Preparation
       998           Mobilization/Demobilization                                   1   LS      $17,500.00       $17,500
       999           Line & grade layout                                           1   LS       $4,000.00        $4,000
      1000           Tree protection fence                                       630   LF         $12.00         $7,560
      1001           Trace out and identify existing underground utility services remaining  1  LS  $3,500.00    $3,500
      1002           Temporay barricades                                           1   LS      $10,000.00       $10,000
      1003           Temporary walks                                               1   LS       $3,000.00        $3,000
      1004           Dust control                                                  1   LS       $2,500.00        $2,500
      1005           Street sweeping                                               1   LS      $15,000.00       $15,000
      1006           Remove & dispose of sidewalks                              4,264  SF          $1.50         $6,396
      1007           Remove & dispose of single trees & stumps                    15   EA        $400.00         $6,000
      1008           Remove & dispose of chain link fence @ Hillside seating area  38  LF         $10.00          $380
      1009           Miscellaneous site demolition not yet depicted                1   LS      $20,000.00       $20,000
      1010          Excavation & Fill
      1011           Building Concrete
      1012             Gymnasium Addition
      1013              Spread Footings