Page 17 - Barr&Barr_Technical Proposal
P. 17

coordination & mechanical coordination. We had weekly foreman’s   with DCAMM and constantly with our subcontractors. Based
           meetings and monthly PM meetings with all subcontractors.    on the complexity of this project the document control/project
           Th  is allowed us to stay ahead of the inherent issues that plague   engineering aspect was critical.   Th  e project engineer’s day to
           every project as well as maintain the schedule which is one of   day responsibility of processing RFI’s, reviewing submittals
           the most important aspects of managing the subcontractors.   and reviewing bulletins is central to the projects triumph.
           Another aspect of subcontractor management is the change order   Barr & Barr issued payments to subcontractors, on average,
           process. As with most large projects cash fl ow is detrimental   between 30 & 45 days. As the project manager on the project,
           to its success. Understanding this, Barr & Barr had a project   I can with certainty state that there was not one concern raised
           manager dedicated to overseeing this process. Th ey constantly   by a subcontractor in regards to monthly payments. Th is is
           met with subcontractors, designers & DCAMM to ensure the   unprecedented for this industry. At the end of this project, the
           process was always moving forward and not becoming arduous   team was subject to a state audit. All paperwork associated with
           and insurmountable.  Performance Rating 5.              this project was required to be 100% complete and accurate.
                                                                   Th  ere were no issues that came up during the audit of this
        4.  MBE/WBE Participation:  As required within all state funded   project.  Performance Rating 4.
          projects Barr & Barr had M/WBE goals that needed to be met
          on this project. In addition to the M/WBE goals, there was a   7.  Working Relationships:  Our main role and responsibility as
          requirement to have a certain percentage of M/W on site as   construction managers is to be the projects ‘communicators’.
          part of the workforce. At the beginning of the project, Barr &   Successful working relationships, or any relationship for that
          Barr developed a plan that outlined how these goals would be   matter, hinges on communication. Th  ere has to be an open
          achieved. Th  e plan was reviewed and accepted by DCAMM’s   line of communication between all team members and all
          compliance offi  cer on a monthly basis. Barr & Barr tracked the   communication needs to be transparent. Barr & Barr takes
          workforce participation on a weekly basis with the subcontractors.   pride in our ability to communicate with all diff erent tiers of
          Th  rough subcontractor buy-out and subcontractor management,   a project, from the owners and designers to the subcontractors,
          Barr & Barr reached and exceeded the goals set forth within the   vendors and site workers. Th  is communication can be identifi ed
          RFP for both the MWBE requirements as well as the workforce   through the weekly meeting with the site workers all the way
          participation.  Performance Rating 4.                    through the monthly exec meetings with the project principals.
                                                                   Performance Rating 5.
        5.  Safety:  With most large construction management fi rms, safety
          is one of the most important aspects of a successful project. Barr   8.  On Site Supervisory Personnel:  Barr & Barr’s team included
          & Barr, as with all projects, went above and beyond the normal   a full time on site staff  from senior project managers and lead
          practices for job site safety. Barr & Barr developed a job specifi c   superintends to fi eld & project engineers and administration.
          safety plan for the project as well as performed safety orientations   Th  is enabled Barr & Barr to confront any on-site issues head
          for each and every worker that was on site. Safety was addressed   on. Th  e team on site was wide-ranging and gave us the ability
          at the weekly foreman’s meetings as well as the weekly owner’s   to manage the complexity of the project. Having all members
          meetings. Weekly tool box talks were required from each of the   of the team on site also allowed for a more seamless overall
          subcontractors on site. In addition to the tool box talks, Barr &   project continuity. Th  is was the foundation for completing
          Barr required the subcontractors corporate safety manuals be issued   this project on time and under budget.  Performance Rating 5.
          and on site at all times. All MSDS sheets were cataloged and
          accessible to all trades and Barr & Barr fi eld staff . Barr & Barr’s   9.  Contract Closeout:  All O&M’s, Warranties & Punch list items
          corporate safety director performed weekly site walkthroughs   were completed and issued shortly following the Certifi cate
          with the superintendents. Reports were formally issued by our   of Occupancy. Both electronic & hard copies of all closeout
          safety director to the entire team (designers, DCAMM, BSU).   documentation were required by the State as well as Bridgewater
          One aspect of this project that shows Barr & Barr’s continued   State University. To ensure the close out documents were
          eff ort to ensure a safe project is the fact that we, along with   acceptable to the end user there were multiple meetings held
          most of the large subcontractors, partnered with OSHA. Th ere   between the subcontractor, Barr & Barr, Bridgewater State
          was a signed agreement between all parties that outlined how   and DCAMM.  Th  is allowed us to streamline the closeout
          the partnership would be instituted throughout the projects   procedure for this project.  Performance Rating 4.
          duration. Part of the partnership program was to have monthly
          meetings with all signed subcontractors, DCAMM & OSHA.
          Th  ese meetings were held for the duration of the project and gave
          everyone the sense that it was a true ‘team’ eff ort to ensure the
          safety of everyone working on site. Having the safety director be
          an integral part of the construction process as well as partnering
          with OSHA allowed Barr & Barr to address issues as they came
          up. It also gave the subcontractors a comfort level knowing that
          B&B actually puts safety 1st and doesn’t just use it as a tag line.
          Performance Rating 4.
        6.  Contract Administration:  As soon as Barr & Barr received
          authorization to proceed from DCAMM, the required insurance
          and bonding paperwork was issued immediately. As stated above,
          the change order process on a project of this size is integral to its
          success. Th  ere were over $6 million of design changes and owner
          requests that Barr & Barr processed and approved with no delay to
          the overall project schedule. Change orders were reviewed weekly
   12   13   14   15   16   17   18   19   20   21   22