Page 66 - FreesStyler® Installation and Startup
P. 66

®
            INSTALLATION AND STARTUP


            Chapter 4 Frame and Carriage Assembly


            Bulkhead Block and Utilities

                   Note:  The hoses when placed in the Boom Channels will require 52” of slack minimum as shown
                          below.

                                                             52”        Measurement taken from one edge of the Boom
                                                                        Channel to the other edge of the Boom Channel


            1)  Move the carriage to the exit end hard stop to ensure the boom does not completely straighten.





















            2)  Move  carriage  to  the entrance end hard stop to ensure that the boom does not completely
               straighten. This is the initial position the machine will be in when routing the utilities.