When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an adequate operating envelope
when placing the Arch.
1) Stand the Arch up at this point in its proper location.
Note: Each Arch head beam weldment has a welded stud on one side of the weldment. These
studs will need to face towards the exit of the bay.
2) Remove the 8 lag bolts from the accessory box and secure the driver side leg to the floor using only
one of the four holes on the base plate. If you have guide rail installed at your site, use the
measurement in the image below for proper location from the drive side leg.
Direction
Of Travel
43-1/2”
Overhead View
Dimensions are taken from the outer equipment leg to the driver side edge of the inside guide rail
3) Square the Arch up to the bay. Secure the passenger side leg to the floor using all four lag bolts,
making sure that the Arch is level in both directions. If so, finish securing the driver side leg to the
floor.
Note: If you have a Utility Arch, proceed to the Neon Strip Kit Installation and Electrical
Connections section. If you have a Spray Arch, continue on to the next step.
Continuing the Arch Assembly
1) Spray Arch Only: Remove the Arch side spray manifolds from the skid. They should have the
nozzle extensions and barbed hose fittings in them already.
2) Spray Arch Only: Slide the two remaining ear clamps over the ends of the blue water hose and
secure the hose to the side spray manifolds.
Before After