            Maintenance


            Routine Procedures
               Daily
                •   Start every wash day with a “Test Wash” to insure proper operation of all equipment.

                •   Inspect the component for clogged nozzles. This can best be done while running the “Test Wash” in
                    the morning. Nozzles can be cleaned by removing the nozzle bodies and tapping or inserting a thin
                    wire into the nozzle opening.

                •   Check the chemical injection pump(s) to insure that the pump is properly primed if applicable. This is
                    done by checking the chemical inside of the clear supply tubing. There should  be  no  bubbles  or
                    breaks in the fluid (if applicable).
                •   Check overall performance for any abnormalities on the first few vehicles washed each day.
                •   Hose down the arch and surrounding area at the end of each wash day. This will remove the majority
                    of the dirt and other debris that builds up during a wash day.
                •   Check for water and chemical leaks after equipment is turned off.
               Weekly
                •   Check all mixing tanks periodically for sludge build-up on bottom. If too much sediment is evident,
                    drain tank and clean (if applicable).
               Monthly
                •   Wash component down with a good degrimer such as Tide laundry detergent and hot water.