INSTALLATION & STARTUP


                      Chapter 22 Initial Startup Procedure


                      Startup Procedure
                      Locate your supplied Programming Manual. Read and understand the following chapters:
                          ·   Programming

                          ·   General Machine Operation
                          ·   General Methods of Using Operator Interfaces
                      You should also familiarize yourself with the standard user screens.

                          MCC
                          1)  Check for proper voltage at MCC, 120V at SCC, and proper voltage at the Dryer Panel.



                           CONSULT A TRAINED ELECTRICIAN. ONLY TRAINED OR AUTHORIZED
                         INDIVIDUALS KNOWLEDGEABLE IN THE RELATED PROCEDURES SHOULD
                               INSTALL, INSPECT, MAINTAIN OR SERVICE THIS EQUIPMENT.

                          2)  Confirm that the power to the MCC is off at load center (building electrical Panel), then turn on all breakers, close
                             the door and turn on the disconnect.