Page 80 - Saber® Installation & Startup
P. 80
INSTALLATION & STARTUP
Chapter 6 Frame and Carriage Assembly
Frame Assembly (Floor Mounted)
8) To assist in the installation process later, drop a plumb bob from the center of the entrance and exit cross-
beam as shown below and mark the floor. Once marked, draw a reference line the width of the bay also
shown below.
Drop plumb-line
from exit surface of
entrance head
beam
Drop plumb-line
from entrance
surface of entrance
head beam
Plumb-bob and
line on the floor
6-18 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL290