Page 15 - TopWinder®
P. 15
®
®
TopWinder
Installation
Frame Assembly
Layout Arm Assemblies
1) Locate both Arm Assemblies and lay them down in the tunnel in the approximate location
where the TopWinder® will be installed. The driver side Arm has two Bearings one attached
to each side of the Mount Plate, refer to the image below.
Passenger Side Arm Assembly
Driver Side Arm Assembly
Filler Strips
Bearing on each side
of the Mount Plate
Conduit Fitting,
Motor & LED Cables
Conduit Fitting,
Motor & LED Cables
2) The Arm Assemblies come with the Filler Strips already installed. Check to make sure the
Filler Strips are secure and are the proper length.
3) The driver side Arm Assembly will also have two conduit fittings attached and the wires for
the Motor/Gearbox and LED will be extending out of the fittings.
1MANUL755 Belanger, Inc.® * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 11