Page 67 - Sudzer® BL & FM
P. 67
®
SUDZER BL & FM
Chapter 4 Sudzer® FM Installation
Sudzer® FM Startup
Initial Start Procedures
1) Working with a local chemical supplier set the chemical to water ratio in the delivery system to
the desired setting.
2) Using the controller force on the function(s) for the lights and chemical delivery.
3) On the MixStir® turn the Pneumatic Regulator to 20psi and the Chemical Solution Regulator
on the pump to 40psi and inspect the entire machine for foam. The foam should be coming
out of all the nozzle tips at about the same consistency. If one or more of the tips are not
passing fluid, turn off the functions to inspect and clean the spray nozzles. Make sure that
there are no water leaks at any of the hose connections or nozzles.
4) After inspecting the Sudzer® FM and confirming there are no leaks and that foam is coming
out of all of the nozzle tips you can adjust the ratio of the chemical/water mixture. Try to find
the best combination of settings that will produce the desired foam but uses the least amount
of chemical. This can be done by changing out the tips that are supplied with the HydroMinder
on the MixStir®.
5) After all of the settings have been adjusted run a few test washes on various vehicles to
confirm that the desired foam consistency and volume has been obtained.
1MANUL026 Belanger, Inc.® * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 4-17