Page 12 - Funksjoner SCAFFPLANNER - NO
P. 12

Build multiple scaffolds

               If no base line elements are preselected, you are prompted to select one by one base line. If you
               have preselected multiple base lines, scaffolds will be built for all the selected base lines in one run.
               The option “Ask for adjustments” is then ignored. Please mind the console issue mentioned above. If
               you use consoles, you should edit the ConsoleLength parameter on the base lines before running the
               function.






               Build Stairs


               Stairways can be built outside the bays. The height between each stair is defined by each existing
               deck of the bay








































                   1.  Select the appropriate equipment to the stairways
                   2.  Press “Create Stairways” to build the stairway
                   3.  Select a toe board at the bay where you want the stairways to be built.

               The existing toe boards and ledgers outside the bay will be removed. Ledgers at top will be replaced
               by your selection

               To all the lists, but the Stairway, the option <No> is present. Select <No> if the equipment should not
               be added. For instance, ledgers at front can interfere with outer guardrail.
               And if Top End Guardrail Standard is of a type that also contains ledgers, set Ledger at top = <No>