Page 21 - LESSONS LEARNED BY MADARFM
P. 21
REAL TIME ISSUES (BURJ RAFAL TOWER)
Concern Area Issue Cause Risk Impact on Customer
4. Ceiling Leakage A. Water flow control Scaling of the water Interior fit out damage Customer Loyalty
valve leakage due to valve which leads to Slippage on the floor Customer Damage
that rain water falls rusting and ultimately cause injuries Brand Damage
through the ceiling (as failure of the valve. Reputation Damage
shown in video)
1. Operator to be in
attendance for
commissioning
program
2. Add to planned
preventative
maintenance (PPM)
schedule.
21