Page 297 - Eden Meadow 35 houses application as of 12 October
P. 297

Land to the Rear of Eden Meadows, Newington
                                                                                         Ref: PL/GB/13776





























                                                      Figure 2-4: Site Access


               2.2.3    With  regard  to  the  wider  highway  network,  to  the  west,  the  A2  provides
                        connectivity  to  the  Medway  Towns.  To  the  east,  it  continues  to  the  towns  of
                        Sittingbourne  and  Faversham  via  the  nearby  Key  Street  Roundabout  junction,
                        which connects with the A249 Trunk Road, providing access to M2 Junction 5 to
                        the south and Maidstone.


               2.2.4    It is evident the site is well located in relation to the primary and strategic route
                        networks.


               2.3      Walking and Cycling Infrastructure

               2.3.1    A  1.8-metre-wide  footway  bounds  both  the  eastern  and  western  sides  of  the
                        access spine road, with the western footway terminating within the completed
                        development site. The eastern footway continues to the northern boundary of the
                        proposal site. Additionally, as noted above, within the vicinity of the site access,
                        dropped kerbs have been provided on the existing traffic calming island to allow
                        for pedestrian crossing movements to take place.

               2.3.2    Footways are provided on  both sides of the A2  in  the  site  vicinity, measuring
                        approximately 1.5 metres in width. To the west of the site, some 310 metres from
                        the existing site access, the southern footway terminates and pedestrians cross to
                        the northern side of the road to access Newington village centre. The existing
                        footway provision is maintained to a reasonable standard and is street lit.

               2.3.3    In addition to the above, a number of Public Rights of Way (PRoW) are provided
                        across the wider area, as shown in Figure 2-5 overleaf, befitting the semi-rural
                        location of the site. Footpath ZR59, to the north of the site access, provides safe
                        crossing  of  the  railway  line  to  the  north,  continuing  into  the  surrounding
                        countryside.