Page 78 - Best Practices In Knowledge Transfer Programme(KTP) Phase 1
P. 78

IMPLEMENTATION OF
               PROJECT






        Objectives                         1.     To identify constraints and limitations at the liquid fertilizer factory that limit
                                                  productivity of the factory and to propose appropriate solutions.
                                           2.     To improve the management and operation system of raw materials ha-
                                                   handling through implementation of standard operation system.
                                           3.     To improve the efficiency of the fertilizer mixing process by redesigning
                                                  the mixer system that is easy to maintain and operate.

        Methodology                                                     Start



                                                                   Project planning
                                                                    and design of
                                                                    mixing system


                                                                    Installation of
                                                                   support system


                                                                 Fabrication of major
                                                                    components


                                                                Fabrication of work cell
                                                                 for safe and comfort
                                                                 working environment


                                                             Review and improvement of                           67
                                                                the materials handling
                                                             management and operation


                                                                Wrap up and reporting



                                                                        End


        Activities Conducted              The activities consist of six job scopes:
                                          1.     Project planning and design of mixing system.
                                          2.     Installation of support system.
                                          3.     Fabrication of major components.
                                          4.     Fabrication of work cell for safe and comfort working environment.
                                          5.     Review and improvement of the materials handling management and
                                                 operation.
                                          6.     Wrap up and reporting.
        Output
        Industry                           The project provides diverse benefits to the industry. The most significant benefit is
                                           high quality fertiliser being produced consistently from the newly developed liquid
                                           fertilizer mixer.

                                           In addition, the cycle time for mixing process is reduced from 6 hours to 3 hours.
                                           This reduction means low operation cost for manpower and utility cost.

                                           Ultimately the project output can fulfil customer satisfaction and improve the com-
                                           pany profit as well as its sustainability in future.