406 | ChaPter 10 Working With Phasing, grouPs, and design oPtions
Figure 10.73
Phase 1 proposed
layout
4. Using the furniture families already loaded in the project, add furniture to the proposed
space as shown in Figure 10.73.
You’ll add a reception area and other office furniture. Add desks, tables, shelving, and
chairs.
5. Add workstation and chair components to the open office area to the right of the Phase 1
area, but group the assembly before you start copying through the office space.
Use your own judgment and creativity in laying out the new elements in the space. The aim
of this exercise is to become familiar with phasing and grouping. Figure 10.74 illustrates the
space in a perspective view. Note that the demolished walls are not being shown.
Figure 10.74
Phase 1 proposed
layout in perspec-
tive view