DELIVERY GROUPS


















                                                                                                         NAVFAC MID-ATLANTIC | P-947 WELDING AND
                                                                                                         REPAIR SHOP FACILITY SAFETY MEETING
                                                                                                         ALBANY, GEORGIA



                                                                                                           SAFETY
                                                      NAVFAC SOUTHEAST | FLEET READINESS CENTER HANGAR 101 REPAIRS  The division experienced a decrease in our
                                                                        NAVAL AIR STATION JACKSONVILLE, FLORIDA
                                                                                                           contract partner recordable injuries from seven
                                                                                                           to four. While still an unacceptable value, we
                                                                                                           appreciate the efforts to keep more contract
          CHALLENGES                                       NEW PROJECTS                                    partners safe. The team continues to focus on
          A claim will likely result from one ongoing      The USCG Fort Macon Hurricane Rebuild and       training and incident prevention in 2023, with
          2019 NAVFAC Southeast P-720 AUTEC Austere        Zone 2 OSS Radar Facility are the two newest    the goal to eliminate all injuries on our projects.
          Quarters project. A base closure brought on      projects for the division. Although awarded
          by the pandemic, client-implemented barging      in 2021, Fort Macon completed the design       “ I appreciate Haskell’s commitment
          adjustments, base access issues involving foreign   efforts and early construction activities in
          national workers and other challenges have       2022. This project is well underway and is      to completing a high-quality
          impacted the AUTEC project. The division profit   expected to maintain profitability through     facility in a safe manner and
          and contribution were bridled by a $2.7 million   to planned early-2024 completion. The Zone
          loss taken on the project. A Request for Equitable   2 OSS facility is in the design phase and early   demonstrating agility and
          Adjustment (REA) is being drafted to recover the   buyout is underway. We will continue to       proactiveness in overcoming
          bulk of cost overruns due to the government’s    implement the improved approach to acquisition
          actions. It is anticipated that the government will   and execution to enhance project results.   challenges while operating in
          reject the REA resulting in the conversion to a                                                  the pandemic environment.”
          certified claim. Despite another successful project
          start and buyout, Zone 2 OSS Radar Facility had
                                                                                                           RAFAEL ENRIQUEZ, NAVFAC SOUTHWEST, SUPERVISORY
          a significant error in our mechanical estimate                                                   GENERAL ENGINEER AT FACILITIES ENGINEERING AND
          resulting in a full write-down taken in 2022.                                                    ACQUISITION DIVISION COASTAL CAMPUS