ESTIMATING + PROCUREMENT


                        SET YOUR PROJECT UP FOR SUCCESS

                       The goal of preconstruction and procurement activities is to set-up the project for success.
                       Mega Projects have amplified or unique challenges that require amplified or unique
                       solutions. The following describes those challenges and methods of approach.



                        STAFFING CONSIDERATIONS


                                                                                  MATCH RESOURCES
                                          IDENTIFY NEED
                                                                                        TO NEED

                         ESTIMATE              CLASS 1 = HIGH DEGREE OF WORK      CLASS 1 = LARGE TEAM
                         CLASSIFICATION        CLASS 5 = LOW DEGREE OF WORK       CLASS 5 = SMALL TEAM

                                               FACILITY, MECHANICAL, ELECTRICAL,   GENERAL ESTIMATORS AND/OR
                         DETERMINE             PROCESS, PACKAGING, CONCEPTUAL     SUBJECT MATTER EXPERTS
                         REQUIRED
                         SKILL SETS                                               ASSIGN A PERSON WHO TIES ALL
                                               ESTIMATING INTEGRATION MANAGER     ESTIMATES TOGETHER, IDENTIFIES
                                                                                  OVERLAPS AND MISSING SCOPE
                         CALCULATE
                         VOLUME OF             THE AVERAGE MEGA PROJECT           ASSUME A SCOPE MANAGER CAN
                                               HAS 86 BID PACKAGES OR >250
                                                                                  ANALYZE 1-3 BID PACKAGES
                         SUBCONTRACTOR         QUOTES TO REVIEW                   PER WEEK
                         ENGAGEMENT
                         DETERMINE TIME-       3 OR 4 MONTHS? SEE PRECON TIMELINE"   SELECT TEAM BASED ON
                         FRAME                 SECTION FOR SUGGESTION             ALL FACTORS



                        DETERMINE TEAMS PER BID PACKAGE



                               SCOPE LEAD                     ESTIMATING                   DESIGN


                               SCOPE MANAGER                  CSA ESTIMATOR                 CIVIL ENGINEER
                                                              MECHANICAL                    ARCHITECT
                                                              ESTIMATOR
                                                                                            STRUCTURAL
                                                              ELECTRICAL
                               OPERATIONS                     ESTIMATOR                     ENGINEER
                                                              PROCESS ESTIMATOR             MECHANICAL
                                                                                            ENGINEER
                               SR PROJECT MANAGER
                                                              PACKAGING
                                                              ESTIMATOR
                               PROJECT MANAGER                                              ELECTRICAL
                                                                                            ENGINEER
                               ASST. PROJECT
                               MANAGER                                                      PROCESS
                                                                                            ENGINEER
                                                                                            PACKAGING
                                   Understanding the scope and volume of the project        ENGINEER
                                   is imperative to right-size the team assigned to that
                                   project. The above are a few considerations to match the
                                   resources to the need. Once determined, communicating
                                   who the resources are per bid package lets the multi-
                                   discipline team know who to coordinate with.


        16                                                                               MEGA PROJECTS PLAYBOOK | 2021
                                CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION.  FOR INTERNAL HASKELL USE ONLY.
   14   15   16   17   18   19   20   21   22   23   24