ESTIMATE CLASSIFICATIONS



              CLASS                 CLASS 5          CLASS 4          CLASS 3          CLASS 2           CLASS 1

                                                  Cost History/                                       Substantially
                                    Verbal                         Conceptual AE        Design
              Description                          Parametric/                                         Complete
                                  Description                         Design        Development
                                                      Study                                              Design
                                                                                                     Permit Issue or
                                                  1 Floor Plan +   >1 Drawing per      30-90%
              Design                  ---                                                             Construction
                                                  Basis of Design    Discipline       Drawings
                                                                                                         Issue


            DESIGN/ESTIMATE FUNNEL


                                 20%
                                                 15%
                                                               10%
                                                                               5%
                                                                                                DESIGN
                                                                                                VARIABILITY

                                                                                                ACTUAL
                                                                                                COST


                                                                                                ESTIMATE
                                                                                                VARIABILITY
                                                                15%            5%
                                                 25%
                                 30%

                         PHASE 1        PHASE 2       PHASE 3                PHASE 4
                        (CLASS IV)     (CLASS III)    (CLASS II)             (CLASS I)
                       Rough Order     Conceptual     Preliminary            Detailed
                       of Magnitude    Project Plan    Design               Design Plan
                       Cost Accuracy   Cost Accuracy   Cost Accuracy       Cost Accuracy
                       +50% to -30%   +40% to -20%   +25% to -15%           +10% to -10%



            PROCESS ESTIMATING PHASES


              CLASS                 CLASS 5          CLASS 4          CLASS 3          CLASS 2           CLASS 1
                                                                    Substantially
              Basis of Design     Preliminary     50% Complete                          Locked           Locked
                                                                     Complete
                                                                                     Substantially
              Equipment List      Conceptual       Preliminary     50% Complete                          Locked
                                                                                      Complete
                                                                                     Substantially
              Process Flow        Conceptual       Preliminary     50% Complete                          Locked
                                                                                      Complete
                                                                                     Substantially
              Floor Plan              ---          Preliminary     50% Complete                          Locked
                                                                                      Complete
                                                                                                      Substantially
              P&IDs                   ---          Conceptual       Preliminary     50% Complete
                                                                                                       Complete

                       Estimate Classifications allow the team to have the same expectations for
                       design progress and corresponding estimate accuracy.


            HASKELL | WE CREATE THINGS THAT MATTER                                                                 17
                                    CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION.  FOR INTERNAL HASKELL USE ONLY.
   15   16   17   18   19   20   21   22   23   24   25