NICARAGUA  Cement  Nagarote Grinding Station

                           Energy

                           Solar park to cover 35%

                           of all electricity needs



                           Opportunity
                                                   reduce the amount of
                           To improve energy
                                                   energy purchased from
                           costs while increasing   electrical service to
                           competitiveness and the   the grid.
                           product’s profit margins.
                           Power prices in Nicaragua   Results
                           are the highest in Latin   Solar Project with an
                           America, close to 170   installed capacity of
                           USD/MWh. In Nagarote,   3,383 kW DC (2,750 KW AC)
                           electricity cost represents   composed of 5,208 solar
      Marcelo Arrieta      48% of variable cost per   modules and 12 inverters
          CEO              tonne of cement.        with 255 kW of capacity.
                           Solution                •   Investment:
                                                    3 MCHF
                           Design, procurement, and   •  Generation capacity:
                           installation of a 3.4 MWp
                                                    5.21Gwh/Year
                           ground-mounted fixed-tilt   •  Self-consumption: 35%
                           solar photovoltaic energy
                           plant to interconnect   •  Payback: 4.7 years
                                                   •   Estimated annual
                           with the existing Holcim
        Ada Alvarez                                 savings: 660 kCHF
         Head of
       Environment