1.2.3 CONSTRUCTION OF RUBs
3 RUBs have been commissioned till Oct’ 2022 out of target of 12.
Progress up to
S No Mode of elimination Target Balance
31.10.2022
1 By RUB/LHS 12 3 9
2 RUBs Box casting completed & Box pushing completed at LC No.33 and Box
pushing in progress at LC No.66.
Action plan for elimination of balance LCs
TDC for LC
S No Section LC No. Remarks
Closure
1 KZJ-BPQ 33 Dec-.22 Box pushing completed
2 KZJ-BPQ 66 Dec-.22 Box pushing in progress
3 KZJ-BPQ 75 Jan-23 Box casting completed
4 KZJ-BPQ 37 Feb-23 Box casting in progress
5 KZJ-KI 86 Jan-23 Thrust bed in progress
6 KZJ-KI 68 Jan-23 Thrust bed in progress
Agreement was terminated
7 KZJ-KI 115A Feb-22 due to slow progress of work.
Fresh tender called
Agreement was terminated
due to slow progress of work.
Agency approached
8 KZJ-KI 74 Honourable High court of
Telangana State. Parawise
remarks have been
submitted to the Railway
advocate.