Page 50 - GM E-BOOKLET 2022
P. 50

1.2.3 CONSTRUCTION OF RUBs


               3 RUBs have been commissioned till Oct’ 2022 out of target of 12.

                                                                  Progress up to
                    S No    Mode of elimination  Target                                   Balance
                                                                    31.10.2022


                      1          By  RUB/LHS            12                3                   9


               2 RUBs Box casting completed & Box pushing completed at LC No.33 and Box

                 pushing in progress at LC No.66.

               Action plan for elimination of balance LCs



                                                        TDC for LC
                   S No      Section       LC No.                                 Remarks
                                                         Closure


                     1      KZJ-BPQ          33          Dec-.22          Box pushing completed
                     2      KZJ-BPQ          66          Dec-.22           Box pushing in progress

                     3      KZJ-BPQ          75           Jan-23           Box casting completed

                     4      KZJ-BPQ          37           Feb-23           Box casting in progress
                     5        KZJ-KI         86           Jan-23            Thrust bed in progress

                     6        KZJ-KI         68           Jan-23            Thrust bed in progress

                                                                       Agreement  was  terminated
                     7        KZJ-KI        115A          Feb-22       due to slow progress of work.
                                                                       Fresh tender called

                                                                       Agreement  was  terminated
                                                                       due to slow progress of work.
                                                                       Agency            approached

                     8        KZJ-KI         74                        Honourable  High  court  of
                                                                       Telangana  State.  Parawise
                                                                       remarks        have       been
                                                                       submitted  to  the  Railway
                                                                       advocate.
















                                                           48