Page 26 - HSSE Contractor Requirement
P. 26

HSSE REQUIREMENT FOR CONTRACTOR, ALLO TECHNOLOGY
                                                                                                   EDITION 01



                   b)   The Contractor shall at no cost to the Employer be responsible for the medical welfare of its own
                        and the subcontractor’s employees and shall take care of arrangements for medical attendance,
                        treatment or hospitalization if and when necessary and will arrange suitable insurance coverage
                        for such contingencies.
                   c)   The Contractor shall at its own expense have fully equipped medical facilities throughout the
                        work’s execution, as per the latest DOSH’s Guidelines on First Aid in the Workplace.
                   d)   The Contractor shall identify and assess the potential risk of high noise area and be responsible
                        in the provision of risk reduction mitigation measures such as but not limited to engineering
                        control e.g. provision of barrier and segregation, administrative control e.g. provision of signage
                        at identified area for its employees, the subcontractor, and visitors.
                   e)   The Contractor shall provide required first aid equipment in accordance with the Factories and
                        Machinery Act 1967 and other applicable legislations.
                   f)   The Contractor shall ensure that its personnel and the Subcontractor’s personnel shall maintain
                        a high standard of hygiene in connection with the performance of the work.
                   g)   The Contractor shall keep record on the occupational health documents at the work site and
                        must be made available upon request.

               5.4.  Temporary Electricity Supply
                   a)   The Contractor shall provide and maintain all necessary temporary electricity power supply for
                        the works. The supply shall have sufficient capacity to meet the power requirements for the
                        whole of the works inclusive of all items included as Prime Cost and Provisional Sum as well as
                        the Contractor’s plant and equipment.
                   b)   Provide  all  temporary  switchboards,  main/sub  main  reticulation  cables,  distribution  boards,
                        wiring, fittings, metering, protection housing of TNB’s equipment, protection of the Contractor’s
                        equipment, switchgears and transformers including all necessary liaison with TNB.
                   c)   The Contractor shall arrange separate and sufficient power supply for testing of mechanical and
                        electrical installations included in the works. The detailed testing requirements shall meet the
                        specialist requirements of each installation.
                   d)   Provide a  network of  electrical  ring  circuit on  every  floor  of  the  building  to  serve  adequate
                        number of 13 Amp. socket outlets for hand tools.
                   e)   If temporary power supply is unavailable from TNB and the available supply is not sufficient to
                        meet the requirement of this project, generator set shall be used subject to the approval of TNB
                        and Chief Electrical Inspectorate of Malaysia. All fuel and replacement parts of the generators
                        are to be borne by the Contractor.


               5.5.  Electrical Safety
                   a)   The contractors shall make themselves thoroughly conversant and conform with the Electricity
                        Supply Act 1990, Electricity Regulations 1994, IEE Wiring Regulation and TNB Electrical Safety
                        Rules governing any work they may have to undertake in any electrical installation or system.
                   b)   Only Energy Commission (EC) Competent Person can work, operate or be in control of any work
                        on operation electrical equipment in line with Section 23 of Electricity Supply Act 1994 and
                        Regulation 60 of Electricity Regulations 1994.
                   c)   The Contractor shall inform The Employer and TNB representatives in advance of any site power
                        supply requirements. Taking electrical supply from any outlet without prior approval of TNB is
   21   22   23   24   25   26   27   28   29   30   31