Page 26 - KRCL ENglish
P. 26

(A view of Murdeshwar loop line)

                   6.3  Rolling Stock Component Factory, Ratnagiri

                         The Rolling Stock Component Factory is being built by KRCL as a modern, platinum
                         rated, green and energy efcient factory for Central Railway to overhaul rolling stock
                         bogies, assemblies and components. It is being constructed at Additional Parshuram
                         Lote MIDC on 50 acre land. The turnkey contract for construction of the Rolling Stock
                         Component Factory was awarded to M/s Tata Projects Ltd. on 12.7.2019 at ` 392.59
                         Crore. The contract for Project Management services was awarded to M/s Rass Project
                         Consultants  Ltd.,  Pune.  The  Design  of  Factory  Complex  has  been  nalised.  The
                         boundary  wall,  land  development  work  has  been  completed  and  the  work  of
                         construction of Factory Sheds is underway. Critical machinery and equipment for LHB
                         bogie  overhaul  has  been  procured.  33KV  Power  supply  shall  be  provisioned  by
                         MSEDCL. The expenditure (provisional gures) during the year has been ` 77.84 Crore
                         against the target of ` 75 Crore.






















                               (The schematic view and the foundation work at factory site)

                   6.4   Roha-Veer Doubling Project

                         Doubling  of  track  in  Roha  –  Veer Section (47km) involves  construction of  11 Major



                                                             24
   21   22   23   24   25   26   27   28   29   30   31