4 Financial Progress achieved till March 2020 ` 597.57 Crore
(88.98%)
5 Physical progress achieved till March 2020 Lead line- 100%
ROR line- 90%
6 Date of completion for 1st stage Completed on 21 st
(Lead line) November 2019
st
7 Target date of completion for 2nd stage (ROR line) 31 March 2021
8 Total no. of bridges 30 nos.
9 Total Earthwork (Embankment and cutting) 41.50 Lakh cum
10 Total Track Length 43 Km
11 Track linking completed 27 Km
(A view of Br. No. 12 at Km. 06/830 (12x30.5 m Composite Girder)
(1st Locomotive movement on 21.11.2019)