4   Financial Progress achieved till March 2020  ` 597.57 Crore
                                                                       (88.98%)

                             5   Physical progress achieved till March 2020  Lead line- 100%

                                                                       ROR line- 90%
                             6    Date of completion for 1st stage     Completed on 21 st

                                 (Lead line)                           November 2019
                                                                         st
                             7    Target date of completion for 2nd stage (ROR line) 31 March 2021

                              8  Total no. of bridges                  30 nos.
                             9   Total Earthwork (Embankment and cutting)  41.50 Lakh cum
                            10   Total Track Length                    43 Km
                            11   Track linking completed               27 Km
























                             (A view of Br. No. 12 at Km. 06/830 (12x30.5 m Composite Girder)























                                        (1st Locomotive movement on 21.11.2019)