6.10 Mangalore Renery and Petrochemicals Ltd. (MRPL) siding work at Thokur Railway
Station
KRCL agreed to the request of M/s MRPL for construction of Private siding at Km.738.130
from the Thokur Railway Station on “Deposit term Basis” and agreement was signed by
both KRCL & MRPL on 31.10.2016. The work of construction of MRPL siding including
Earthwork, Bridges, Track linking and approach road near Thokur Station is completed
on 30.05.2019. Financial progress achieved in the nancial year 2019-20 is ` 13.22 Crore
against target of ` 13.00 Crore. The loading operation in the new siding is commenced.
Engine Trial at MRPL siding on First freight train entering on MRPL siding
30.05.2019 and loading of petcock started on 18.10.2019
6.11 Closure of LC 61 by constructing RCC precast box in Karwar Region
The work construction of 3.00mX2.50m RCC precast box (segmental) by cut and cover
technic in lieu of LC 61 at Km 549/000 between Gokarna Road and Kumta is completed in
all respect. LC 61 gate is permanently closed.
(Image of RCC precast box)