11. SAFETY
• Konkan Railway has accorded highest priority for Safety in train operations with quest for
zero accidents. The personnel involved in train operations have been kept up to date with
their working knowledge through regular training, workshops, interactions etc.
considering immediate requirements. During the year there was one consequential train
accident of Fire in AC 3 tier (B-4) coach of Train No.12618 (Mangala express) in Bijoor
and Senapur section on 28.04.2019. There was no casualty/injury in the accident. The
responsibility for this accident was attributed to personnel belonging to Southern
Railway. There was no case of SPAD. CRS / Central Circle conducted the annual safety
inspection of ROHA-TOK section on 11th & 12th April 2019 along with C&MD, Directors
and concerned HoDs. Also, CRS/CC along with C&MD, Directors and concerned HoDs
conducted inspection of RE works between Thokur-Bijoor stations on 12.03.2020 in
connection with commissioning of RE.
• Inter Railway Safety Audit of Karwar Region by a team of PCSO and SAG ofcers of South
Eastern Railway was conducted from 28th to 30th November, 2019. Intra Railway Safety
audit of RN & KAWR region have been conducted in the month of December 2019 and
February 2020 respectively. PED/Safety & ED(Mech)/Safety Railway Board have
conducted safety review meeting at Madgoan on 12.10.2019. A joint mock exercise with
NDRF / 5 Battalion Pune, has been organized at VEN station on disaster management on
13.10.2019. Also, to check the functioning of SPARM cum MFD Van with MFD Equipment
and alertness of staff two each at RN & VEN full scale Mock Exercise has been
conducted.
• During the year, 03 SAG level executives have attended Safety Management training
courses at IRITM/Lucknow. To inculcate safety rst culture 14 nos. of safety
circulars/JPOs have been issued. 56 Safety Seminars/ workshops were organized
wherein total 2874 nos. of Safety Category Staff participated and 32 nos. Safety Drive
were launched. Also, SWRs were prepared in view of Doubling works, additional loop
lines, new stations, RE works, EI working, etc. In addition to above, to ensure safety in
train operations and for system improvement, 26608 nos. of safety inspections covering
various safety installations have been conducted during the year.
12. GLOBAL COMPACT
Corporation is among the rst few PSUs, who is a signatory to Global Compact. The
Corporation strives to comply with the 10 (Ten) principles of United Nations Global
35