10.4  Wi-Fi has been provided at all Stations of KR as a part of Ministry of Railway's 100 days
                         Action Plan, under MoU of IR with M/s. TATA TRUST and commissioned on 22.09.2019.

                   10.5  15 pairs of “Block panel along with Universal Fail Safe Block Interface (UFSBI) and Block
                         proving by Axle counter (BPAC)” provided in 15 Block sections, facilitating easier/faster
                         operation for station master including Automatic Block closure, resulting in improved
                         reliability, making block circuit RE t. This also upgraded the standards of Interlocking
                         from STD II (R) to STD III (R).











                   10.6  Engineering “Special Class” Manned Level crossing gates No 62 & 89 are interlocked
                         independently with combination of signals. Also, 'C' Class LC gate Nos 76, 78, 79 & 90
                         are interlocked with Station signals. Sliding booms are provided at LC Nos 62, 76, 89 &
                         90  to  improve  the  reliability  as  redundancy  in  operation  of  Level  crossing  gates  is
                         provided. In addition to this, at 15 LC gates, Mechanical Lifting Barriers have been
                         replaced with Electrical Lifting barriers in connection with Track doubling work (11 gates)
                         & Interlocking of LC gates (04 gates).
                                                  Manual operated LC gate being
                                              replaced with Electrical operated Gate








                                   MLCG with  Booms  manually  MLCG with  Booms  Electrical
                                            operated             operation & boom locking
                   10.7  Replaced conventional aspects of Subsidiary Signal aspects with LED aspects at 53
                         stations (Excl. KOL, MNI, VEER, MAO, MJO which are under progress in Patch Doubling
                         &  RVNL  works)  to  improve  the  visibility  of  signals  and  also  reducing  the  power
                         consumption.