Page 16 - McD_ROTF DRAINAGE & PIPED SERVICES_Neat
P. 16

Drainage & Piped Services Standard Specification
Version 2014-1

                2. The design, drawing and fabrication of brackets, supports and associated fixings.
                3. The provision of design, installation, working and fabrication drawings, including

                     the co-ordination of detailed installation elements within the building fabric.
                4. The selection and suitability of all items specified by performance.
                5. The design of the fire alarm installation shall lie with the specialist contractor

                     through the Contractor.
                6. The BMS design and installation to meet the design intent of the BMS

                     performance specification

1.2.23 Materials and Equipment

             The Contractor is to be totally responsible for ensuring that all nominated firms
             supplying equipment or carrying out work, comply with these Employers Requirements.

             Where items are specified by name and/or model number, it is the Contractor's
             responsibility to ensure that the item specified and supplied meets the performance
             criteria given.

             All materials are to be in accordance with the types and manufacture described in this
             Specification. Where the Contractor desires to use materials differing from those
             described, alternatives may be offered wherever he considers this desirable. Any
             alternatives offered must be approved in writing by PM.

             The Project Manager reserves the right to inspect materials on site and to reject any
             materials not complying with this Specification.

             The cost of any dismantling and re-erection of the installation occasioned by the
             removal of rejected materials are to be borne by the Contractor.

             The Contractor is to ensure that delivery, assembly, erection, testing, setting to work
             and completion by a nominated firm including any variations affecting that firm,
             complies with the requirements of this Specification.

             The cost to the Contractor of ensuring the above procedures are carried out is to be
             borne entirely by the Contractor.

             In the event of the Contractor nominating an alternative manufacturer for specified
             equipment, he is to be responsible for ensuring that it is equal or better in performance
             to the original, and that it is dimensionally suitable for the installation. Any additional
             costs arising out of the necessity of re-planning, relocating or refitting equipment due
             to the use of such alternative equipment is to be borne by the Contractor.

1.2.24 Defects

             Prior to Practical Completion and when the Contractor has satisfied himself that all
             work is complete and defect free in accordance with the Employers requirements, the
             Contractor is to offer the works to the Project Manager for inspection. The Project
             Manager shall prepare a Schedule of Defects and formally issue them through the
             Contractor for action by the Contractor. The Contractor is to inform all parties when he
             considers all remedial works have been complete.

             Concealed or buried work is to be inspected and tested in the presence of the Project
             Manager before any permanent covering is applied. The Contractor is to give due
             notice, , to the Project Manager when the work is ready for inspection and the Project
             Manager shall, without reasonable delay, carry out his inspection and/or witness the

McDonalds Restaurants Ltd                         1 / 11
   11   12   13   14   15   16   17   18   19   20   21