Drainage & Piped Services Standard Specification
Version 2014-1
1. All testing and commissioning as prescribed elsewhere is complete to the
satisfaction of the PM and record of tests has been provided by the Contractor.
These are to form part of the maintenance manual to be supplied.
2. Spares, tools, equipment etc have been passed to the Client.
3. Operation and Maintenance manuals, instruction charts, diagrams, record
drawings etc. have been submitted, approved and supplied.
4. A complete demonstration of every service has been carried out with full
functional operational controls tested and demonstrated and instructions given
to Client's staff to show proper working.
1.2.16 British Standard Specifications
All equipment, materials and workmanship are to comply fully with the requirements
of the relevant British Standard and/or its European equivalent (BS EN ISO)
1.2.17 Specialist Trade Attendance on Plant and Equipment
The Contractor is to arrange and make payment for specialist tradesmen to visit site,
adjust and put into working order all items of specialised plant and equipment supplied
under the Contract.
1.2.18 Cleaning Down Equipment
On completion of the works or section of the works any new item and/or existing item
of equipment that has been soiled (by the Contractor or his Sub-Contractors) are to be
thoroughly cleaned internally and externally and where applicable polished by the
Contractor.
1.2.19 Maintenance of New Equipment
All items of equipment whether put into operation before the completion of the
Contract or not must be maintained in perfect order by the Contractor until the
Practical Completion of the installation or until an agreed section of the installation is
officially handed over to the Client.
1.2.20 Discrepancies
Any apparent discrepancies within the Employers Requirements are to be noted at the
time of tendering. No claim for extra costs shall be considered in respect of any item
described in the Employers Requirements.
1.2.21 Testing and Commissioning Of the Works
The Contractor is to undertake a pre commissioning exercise of the installations to
prove correct operation of lighting control and other interlocked systems, air and water
flow rates and temperatures and water condition.
The Contractor is to carry out all necessary commissioning and testing, both as the
installation proceeds and on completion to ensure the correctness of the installation
and its compliance with the following (where no suitable code exists for commissioning
an item of plant, the manufacturer's recommended method of commissioning should
be used). The Contractor shall be required to re commission the entire system
installations where all or part of the systems has been effected/altered by the works
required by these employers’ requirements: