Drainage & Piped Services Standard Specification
Version 2014-1
between centres and are to be approximately 11.0mm from the edge of the sheet to
the centre of the holes.
The name of the manual is to be shown on the front and spine of the cover. Where the
handbook is comprised of more than one book or volume each book or volume is to be
numbered. The book or volume number is to be shown on the front and spine of the
cover.
In addition to the above the contractor is to provide a building logbook in accordance
to the requirements of the Part L of the building regulations based on the format of
CIBSE TM31 guidance and template.
1.2.13 Contractor’s Obligations
The general MEP preambles detailed herein are to be read as supplementary to the
main Contract Conditions. Where conflict arises, the Contractor is to bring to the
attention of the PM for clarification prior to the submission of his Tender.
The Contractor is to take due notice of his obligations in this regard and make
allowance within his tender for compliance thereto.
The Contractor is not to use the site for any purpose other than the Contract Works.
The Contractor is to allow for providing the following information following acceptance
of his tender:
1. Detailed programme for design and installation.
2. Detailed labour resource histogram and regular updates throughout the course
of the Contract Works.
3. Monthly progress reports and attendance at site meetings.
4. All builderswork’s information, drawings and schedules required in connection
with the Contract Works.
The Contractor is to allow for complying with all other conditions and restrictions as
detailed within the Contractor's preliminaries, with particular regard, but without
limitation, to maintenance of services, site cleanliness, maintenance of access routes,
and removal of rubbish.
The Contractor is to allow for liaison with other Contractors, and artists, tradesmen and
Statutory Authorities.
1.2.14 Special Tools and Accessories
Special tools and accessories required for the proper running and maintenance of the
plant are to be supplied by the Contractor and handed to the Client.
The Contractor shall be responsible for obtaining a signed receipt for all equipment
passed to the Client.
1.2.15 Practical Completion
The installations are to only be considered complete when the installations are officially
approved and accepted by the PM.
The installation shall not be deemed complete until: