Drainage & Piped Services Standard Specification
Version 2014-1
The Contractor is to protect, uphold and maintain all pipes, ducts, sewers, service
mains, overhead cables etc., belonging to the Client, the Private or Public Utility
Companies affected by the project during the execution of the Works. The Contractor
is to make good any damage due to any cause within his control at his own expense
and pay any costs and charges in connection therewith.
1.2.10 Co-Ordination
The Contractor is to ensure that full liaison with all Contractors’ engaged on the
Contract takes place, to ensure satisfactory design progress and installation of the
Works.
The Contractor is to co-ordinate his design with other trades to facilitate installations.
Where a number of installations share a common route the installations shall generally
proceed in the following order:
1. Drainage and waste plumbing
2. AC / Ventilation ductwork
3. Sprinkler Pipework
4. Service pipework
5. Electrical work
Where mechanical or electrical equipment is specified by manufacturer's name and
catalogue number it indicates the type and standard of equipment required. The
Contractor is to ensure that the equipment supplied is co-ordinated with other services
and building works, and is suitable to comply with the design performance
requirements and all standards, guides, and regulations.
1.2.11 Dimensions
The Contractor is to take his own dimensions of the buildings or structures for the
purpose of installing the plant and equipment and is to be responsible for the accuracy
of such dimensions.
Reference is to be made to latest Architectural and Structural information.
1.2.12 Definition of Drawings
The following definitions are to be applied to drawings referred to and/or required by
this specification:
Contractors Co-Ordination Drawings, Installation Drawings and Information (Working
Drawings)
From the information provided in the MEPH Specification and drawings, the Contractor
is to prepare all necessary design, co-ordination and installation drawings, shop
drawings, diagrams and schedules to a scale as may be required to illustrate in detail
the arrangements of the various sections of the Contract Works and to identify and
describe the various components for the proper execution and installation of the
Contract Works in accordance with this document in a neat and skilled manner to the
satisfaction of the Project Manager.
The design and installation drawings are to be fully co-ordinated with the requirements
of the Sub-Contractors and with the building and its associated services and are to
indicate all necessary dimensions for the integration of the Contracts works properly