Drainage & Piped Services Standard Specification
Version 2014-1

             tests unless he informs the Contractor in writing that he considers the tests
             unnecessary.

             In no instance is concealed or buried work to be covered without being fully tested and
             documented by the Contractor.

             In the event of the Contractor failing to complete all defect works to any area within
             the desired period to the satisfaction of the Project Manager, the Client may instruct
             the Project Manager to achieve the desired completion(s) with whatever assistance is
             deemed necessary.

             The cost of such assistance inclusive of the Project Manager's costs for each and every
             occasion shall be deducted from the Contractor's payments.

1.2.25 Schedule of Rates

             The Contractor is to, as set out in the main contract documents, submit a fully detailed
             Schedule of Rates inclusive of all material and labour rates and indicating all associated
             overheads and profits.

             The Schedule of Rates are to show in detail the quantities, process and extensions used
             in the calculation of the Tender Prices and the Contractor is to accept responsibility for
             the accuracy of any quantities and extensions contained therein and the Schedule are
             to balance with each priced item of the Contractors Tender summary.

1.2.26 Training of Client’s Staff

             The Contractor is to allow for the provision of sufficient skilled personnel, during
             ordinary working hours for the purpose of instructing the Client's staff in the operation
             of the plant.

             The Contractor is to include for all costs in connection with specialist training for the
             Client's staff on operation and maintenance of particular plant or systems (Refer to the
             Particular Specification for any additional specific requirements).

             The Project Manager may at his discretion redistribute days allocated between
             individual systems to suit the store manager's requirements.

1.2.27 Document and Drawings on Site

             The Contractor is to ensure that one copy of the current Design/Installation Documents
             prepared by the Contractor are kept in his office on site at all times and that his staff
             and operatives are fully conversant with same.

             The Contractor is to also include for keeping one set of his installation drawings in his
             office on site upon which he is to keep marked up, on a daily basis the installation
             progress to record the progress of the Contract Works. These drawings are to be kept
             solely for this purpose and are to be kept up to date at all times together with any
             amendments or variations to the works which are to be recorded upon them.

             The "marked up" set of installation drawings are to form the basis of the "Record
             Drawings" required upon completion of the Contract Works as described elsewhere on
             this document.

McDonalds Restaurants Ltd  1 / 12