Page 5 - Bernardon Response to Request for Proposal-Dennis Farm
P. 5

Proposal for Professional Architectural Design Services                  February 11, 2021
                    Dennis House Restoration and Reconstruction                                         Page 3


                        First Floor
                        · Reconstruct the original living room, den, and dining room and utilize as exhibition space.

                           Provide details and finishes to match ca. 1940 appearance as a setting for the exhibits.
                        · Reconstruct original kitchen to its ca. 1940 appearance with exhibits of salvaged household

                           items. Provide details, finishes, and fabricate kitchen cabinetry and countertops to match the
                           configuration and appearance of that period.
                        · Reconstruct the ca. 1940 screened porch.

                        Second Floor
                        · Reconstruct the four (4) bedrooms to ca. 1940 configuration. Provide original details and

                           finishes to match their appearance at that time.
                        · Bedrooms may serve as exhibit, office and/or staff support space.

                        · Reconstruct  the  second-floor  hall  bathroom  to  match  the  original  finishes  and  historic

                           bathtub. Provide traditional style, handicapped accessible sink and toilet fixtures.


                    BASIC SERVICES
                      PHASED IMPLEMENTATION
                        The  DFCLT  has  received  two  (2)  funding  grants  focused  on  different  aspects  of  the  project
                        construction. We anticipate the design work will be undertaken as one project. However, since
                        construction will be implemented in two phases, this proposal is presented in two phases, each
                        with a separate scope and schedule.

                        · Phase 1

                               o  Phase 1.A focuses on the foundation repair. Construction completed in early 2021.
                               o  Phase 1.B includes the design and construction documents for the restoration of the
                                   remainder of the Dennis House.

                        · Phase 2 involves the future construction period service for the Dennis House restoration.

                           Construction is expected to be completed by 2024, dependent on fundraising.