Proposal for Professional Architectural Design Services                  February 11, 2021
                    Dennis House Restoration and Reconstruction                                         Page 5


                        PHASE 1
                        Phase 1.A – Stone Foundation Wall Repairs (continued)
                          SCHEDULE
                          Bernardon  anticipates  that  the  project  schedule  for  design,  bidding  and  construction  as
                          follows:
                           · Kickoff Meeting                                         To Be Determined

                           · Preconstruction Site Meeting                            1 week

                           · Scope Memorandum                                        2 weeks

                           · Construction Phase                                      To Be Determined


                        Phase 1.B – Design Documents for Dennis House Restoration and Reconstruction
                          SCOPE
                          Phase 1B encompasses the full restoration and reconstruction of the Dennis House to its ca.
                          1940 configuration and appearance. The existing timber frame wall sections will be evaluated
                          for reuse and repair; the existing structure will be repaired as required; new structural timber
                          floor, wall and roof framing will be constructed as described in the HSR; replacement of the
                          existing basement floor with a new concrete floor slab; new exterior siding, roofing, doors and
                          windows;  new  interior  partitions,  finishes,  stairs,  doors  and  fittings;  and  new  north  porch
                          foundations, floor, walls, and roof; installation of concealed modern utilities, including geo-
                          thermal heating and cooling, water, plumbing, septic, electrical, lighting, data, and emergency
                          power systems. Bernardon and the consulting engineers (hereinafter the “Design Team”) will
                          provide the following scope of services: removal of the basement floor slab; archeology below
                          the  floor  slab  and  at  the  exterior  perimeter  of  the  foundation  walls;  installation  of  a  new
                          basement floor slab with an underfloor drainage system.

                          1.B.1    DESIGN DEVELOPMENT
                           A.  Kickoff Meeting:  Attend a virtual kickoff meeting with representatives of the Dennis
                               Farm Charitable Land Trust (DFCLT), and others as appropriate to verify the project
                               scope, special requirements and schedule.
                           B.  Field  Survey:    Meet  on  site  to  verify  the  existing  conditions  and  probable  extent  of
                               repairs in sufficient detail to design and prepare construction documents for the Project.
                           C.  Geotechnical  RFP:    The  structural  engineer  will  prepare  a  geotechnical  engineering
                               Request for Proposal (RFP) for the Owner’s use, requesting design parameters for new
                               foundations, under slab drainage, etc.

                           D.  Building Code Review:  Perform a review of the building codes and standards that will
                               apply to the Project.