Proposal for Professional Architectural Design Services                  February 11, 2021
                    Dennis House Restoration and Reconstruction                                         Page 8


                        Phase 1.B – Design Documents for Dennis House Restoration and Reconstruction (continued)
                          SCHEDULE
                          Bernardon  anticipates  that  the  project  schedule  for  design,  bidding  and  construction  as
                          follows:
                           Design
                           · Kickoff Meeting

                           · Design Development                                             8 weeks

                           · Design Development Review Meeting

                           · DFCLT Approval of Design Development Documents                 2 weeks

                           · Construction Documents                                        12 weeks

                           · Construction Documents Review Meeting

                           · Final Refinement of Construction Documents                     2 Weeks

                           · DFCLT Approval of Construction Documents                       2 weeks

                           Bidding and Construction Phase
                           · Future - Please refer to Phase 2 (below)              To Be Determined

                          The schedule assumes meetings, reviews and approvals will be scheduled and expedited in a
                          timely manner. Unforeseen design issues related to the existing structure or delays in agency
                          approvals etc. could negatively impact the schedule.