Proposal for Professional Architectural Design Services February 11, 2021
Dennis House Restoration and Reconstruction Page 8
Phase 1.B – Design Documents for Dennis House Restoration and Reconstruction (continued)
SCHEDULE
Bernardon anticipates that the project schedule for design, bidding and construction as
follows:
Design
· Kickoff Meeting
· Design Development 8 weeks
· Design Development Review Meeting
· DFCLT Approval of Design Development Documents 2 weeks
· Construction Documents 12 weeks
· Construction Documents Review Meeting
· Final Refinement of Construction Documents 2 Weeks
· DFCLT Approval of Construction Documents 2 weeks
Bidding and Construction Phase
· Future - Please refer to Phase 2 (below) To Be Determined
The schedule assumes meetings, reviews and approvals will be scheduled and expedited in a
timely manner. Unforeseen design issues related to the existing structure or delays in agency
approvals etc. could negatively impact the schedule.