               The project phases we have planned in our work activities include:




                        TASK         SCHEMATIC PHASE
                                         •   Project kick-off meeting.
                           01
                                         •   Code research.
                                         •   Calculations.
                                         •   Investigation of mechanical, electrical, plumbing systems to accomplish the
                                             desired result for the project.
                                         •   Preliminary document defining potential MEP/FP system alternatives for
                                             Owner/Architect review and budgeting.
                                         •   Review of any special needs and identifying the most appropriate means of
                                             achieving operational requirements.
                                         •   Prepare and submit S&M applications with that appropriate utility companies
                                         •   Preliminary coordination of utilities with Civil.
                                         •   Attendance at the allocated project/design meetings during this phase.
                                         •   Preparation of a narrative based schematic submission for owner review and
                                             budgeting.




                        TASK         DESIGN DEVELOPMENT
                                         •   Incorporate client input from schematic including MEP system selections.
                           02
                                         •   Perform preliminary equipment selections and mechanical and electrical
                                             space requirements based on budgetary input.
                                         •   Provide proposed domestic water room, plumbing riser locations, proposed
                                             utility connection locations.
                                         •   Provide proposed main electrical room layouts, corridor lighting and power
                                             layouts, electrical distribution closet layouts.
                                         •   Provide proposed common area mechanical shaft locations, corridor
                                             ductwork distribution, and rooftop mechanical equipment layout.
                                         •   Preparation of six (6) prototypical enlarged unit mechanical, electrical, and
                                             plumbing plans for owner/architectural review.
                                         •   Submission for budget confirmation for MEP systems.
                                         •   Attendance at the allocated project meetings during this phase.
                                         •   Participation in value engineering effort if MEP construction costs exceed
                                             project budget.




               Advanced Engineering Inc. | 5561 Pennell Road, Media PA 19063 | 610-361-0700             8/15