Page 29 - Bernardon Proposal for Design Services-1010 Grant
P. 29
1010 Grant Multifamily Building
Bernardon
03/21/2022
WORK PLAN
The project phases we have planned in our work activities include:
TASK SCHEMATIC PHASE
• Project kick-off meeting.
01
• Code research.
• Calculations.
• Investigation of mechanical, electrical, plumbing systems to accomplish the
desired result for the project.
• Preliminary document defining potential MEP/FP system alternatives for
Owner/Architect review and budgeting.
• Review of any special needs and identifying the most appropriate means of
achieving operational requirements.
• Prepare and submit S&M applications with that appropriate utility companies
• Preliminary coordination of utilities with Civil.
• Attendance at the allocated project/design meetings during this phase.
• Preparation of a narrative based schematic submission for owner review and
budgeting.
TASK DESIGN DEVELOPMENT
• Incorporate client input from schematic including MEP system selections.
02
• Perform preliminary equipment selections and mechanical and electrical
space requirements based on budgetary input.
• Provide proposed domestic water room, plumbing riser locations, proposed
utility connection locations.
• Provide proposed main electrical room layouts, corridor lighting and power
layouts, electrical distribution closet layouts.
• Provide proposed common area mechanical shaft locations, corridor
ductwork distribution, and rooftop mechanical equipment layout.
• Preparation of six (6) prototypical enlarged unit mechanical, electrical, and
plumbing plans for owner/architectural review.
• Submission for budget confirmation for MEP systems.
• Attendance at the allocated project meetings during this phase.
• Participation in value engineering effort if MEP construction costs exceed
project budget.