Use and control of MEWP’s



                 •    MEWP’s must have a thorough inspection within the past 6
                      months, weekly inspection, plus a pre-use inspection.
                      Documentation to be held in document holder with operating
                      manual.
                 •    Operator and spotter must be trained in the use of the particular
                      machine. (Spotter requirements set out in MEWP Spotters VS).

                 •    Ground conditions must be suitable for the type of machine.
        3. Working at Height
                 •    Never operate machines outside of manufacturer’s guidelines
                      i.e. overloading, as a crane, carrying materials on handrails etc.
                 •    Be aware of weather restrictions, particularly wind.

                 •    MEWP permit required for each machine. This must set out the
                      exclusion zone and any access restrictions required. Permit
                      authorized by Jacobs Area CS.
                 •    Rescue procedure must be in place in the event of the Operator
                      becoming ill or the machine malfunctioning.

                 •    Agreed procedure must be in place for operating through
                      restricted areas i.e. doorways.
                 •    Be aware of live services within the area.
                 •    Pinch points to be labelled.

                 •    Ensure clips are in place where machines have collapsible
                      handrails.
                 •    100% tie-off to suitable anchor point in all MEWP’s.

                 •    Gate must remain closed when machine is in use.
                 •    Don’t store any items around the controls that could impede use.