Page 71 - Best Practice for Construction Projects
P. 71

Control of lifting operations / crane set up




                •     All cranes must be operated by trained CSCS
                      personnel
        7.Lifting and Transporting Operations
                •     Ensure the lift plan is developed by the Appointed
                      person for cranes. The lift plan must be approved
                      by the PSCS.

                •     The crane will have its annual and 4 year
                      certification. All lifting accessories will have
                      certification.

                •     All cranes must be visually inspected after set up
                      and before each use and a recorded weekly
                      inspection using a GA2 form performed.

                •     The exclusion zone will be set up with barriers
                      and Signage & will adequate for the Planned lift.

                •     There will only be one lifting accessory on the
                      hook block.

                •     Appropriate tag lines will be used on all lifts.
                •     The air horn will be activated prior too and during

                      the lift.
                •     The Slinger / Signaller will have a direct means of

                      communication with the crane operator.