Rigging techniques




                •     All rigging must be carried out by a trained
                      Rigger/Slinger.
        7.Lifting and Transporting Operations
                •     Under no circumstances are persons permitted
                      to rig equipment when not trained to do so.
                •     Use the correct lifting equipment for the job.

                •     All slings and lifting equipment must be visually
                      checked before each use to ensure no damage
                      present. Weekly recorded inspections must be
                      kept on site file.

                •     All lifting equipment must be certified every 6
                      months and certificates kept on site file for
                      inspection.

                •     If you see incorrect or bad rigging techniques
                      report it to a supervisor straight away.
                •     Never join slings together with knots.

                •     Do not run slings over sharp edges without
                      suitable padding.
                •     Rigging points should be planned in advance
                      and use the most appropriate accessories for
                      the task. You may need temporary works sign
                      off / approval from the permanent works
                      designer.
                •     Plan the lift using the appropriate size and
                      tonnage of sling and accessories for the weight
                      of the load.