Page 73 - Best Practice for Construction Projects
P. 73
Rigging techniques
• All rigging must be carried out by a trained
Rigger/Slinger.
7.Lifting and Transporting Operations
• Under no circumstances are persons permitted
to rig equipment when not trained to do so.
• Use the correct lifting equipment for the job.
• All slings and lifting equipment must be visually
checked before each use to ensure no damage
present. Weekly recorded inspections must be
kept on site file.
• All lifting equipment must be certified every 6
months and certificates kept on site file for
inspection.
• If you see incorrect or bad rigging techniques
report it to a supervisor straight away.
• Never join slings together with knots.
• Do not run slings over sharp edges without
suitable padding.
• Rigging points should be planned in advance
and use the most appropriate accessories for
the task. You may need temporary works sign
off / approval from the permanent works
designer.
• Plan the lift using the appropriate size and
tonnage of sling and accessories for the weight
of the load.
3 Visual Standards | Feb. 2019