Dumpsite rehabilitation projects are initiated due to one of the following reasons:
                        Presence of marketable material in the dumpsite that can be excavated for sale or
                         use;
                        Reduction in the closure and post operation monitoring costs of the site;
                        Stipulated  requirement  by  the  owner/regulator  of  the  landfill  to  close  and
                         rehabilitate the site;
                        Presence of toxic wastes within the dump site that poses public health risks;
                        To eliminate potential contamination at source;
                        For redevelopment of landfill site;

               The  main  purpose  of  this  work  is  Dumpsite  Land  Reclamation  through  Bio-mining  of  old
               Dumped Municipal Solid Waste/Legacy Waste, resource recovery and Scientific disposal of
               residual solid waste.

               Dumpsite  reclamation  will  be  done  by  dividing  the  site  into  suitable  sectors/loops  in
               consultation of the Engineer-in-charge based on the priority of land reclamation. The Total
               Station  survey  shall  be  done  at  the  time  of  possession  of  the  site  as  well  as  at  the
               completion of each milestone of physical progress of land reclamation at the site to verify the
               quantities of biominied and remaining legacy waste.

               Usually the top layer has fresh waste, dust and may have several materials in the active
               biological  state.  This  layer  is  to  be  stabilized  through  application  of  Bio-Culture,
               herbal/biological sanitizers, inoculants or through any suitable scientific method. Odour shall
               be controlled and minimized through application of deodorant or scientific method.

               Excavating the existing mixed compacted MSW in the land portion allocated/earmarked by
               the  Authority  and  sieving  them  by  Mechanical  sieving  machine  or  any  other  suitable
               technology  proposed  and  accepted  by  the  Engineer-in-charge.  The  excavated  materials
               shall be quantified (in Cubic meter, based on number of vehicles trips and capacity) after
               excavation and record of the same shall be maintained.

               Segregate the excavated MSW in into as many kinds and categories as possible of Useful
               Material such as compost, soil conditioner, recyclables, raw RDF, filler material (Soil, C&D)
               and Un-useful material such as residual Solid Waste.

               Packing,  storing,  stacking,  selling,  diverting  for  recycling,  marketing  and  recycling  of  all
               Useful  Material  within  thirty  days  of  segregation  at  the  cost  of  the  Contractor,  without
               accumulation in the storage facility at the project site beyond thirty days.

               Baling, packing, stacking, storing and sale of non-recyclable fraction of high calorific as raw
               material to RDF producer/ user or sale to waste to energy or co-processing in cement plants
               or to thermal power plants. The recyclable can be store separately and sell to the recycling
               material vendors.

               The  compost/decomposed  organics  recovery  by  passing  the  materials  through  4  mm  IS
               sieve.

               Stacking, transporting, spreading and compacting the segregated C&D, Soil and Stone as
               filler material in low level and depression area within the site and prepare well compacted
               and  clear ground for  proposed  development  at site  or  disposing  such material  in  the  low
               level area or use in earthen embankment etc.

               The typical activities of biomining are represented in flow chart in Figure 4-1.