Survey Report        Contents           Overview           Services           Internal           External           Total Est. Costs   11



       WC




















       WC                                  Lighting not IP rated               No sealant


















       Gap in flooring
       Details / Defects / Issues: Yes. Items of concern have been listed below.




       Extraction

       No form of mechanical extraction is fitted within the room.  You are advised to install a mechanical means of
       ventilation, in line with Approved Documents F and L of The Building Regulations 2010.  This will need to be in the
       form of an extractor fan with a 15 minute overrun timer facility.  A 3-pole isolation switch will also need to be
       installed. You are advised to seek further advice from an electrician and undertake remedial work as recommended.


        Estimated Costs £400-500.00





       Electrical Installation

       The lighting is not suitably IP rated and presents a safety issue.  As part of any electrical repairs and upgrades the
       lights will need to be replaced with IP rated fittings.


        Estimated Costs £120-150.00