CDM
            To comply with CDM Regulations and support the site Health
            and Safety Plan, method statements will be provided for
            each site activity covering the following elements:

            Design                                              Work in confined spaces
            Procurement, delivery and storage                   Hot work, such as cutting and welding

            Resourcing                                          Working at height

            Works by others                                     Access to lifts

            Installation                                        Working on Low voltage electrical equipment
            Testing and Commissioning

            The method statements will be written to suit the requirements
            of the main contract programme and the working procedures
            of other trades.  Risk Assessments will be prepared for each
            activity to compliment the method statements.  Design Risk
            Assessments will be prepared, as appropriate, to ensure
            that all systems are safe in use.
            Permit to Work system (PTW)

            The Comserve PTW system is a formal process through
    36      which high  risk activities are monitored and controlled
            through a process of physical signature and also form part
            of a Safe System of Work (SSoW). The PTW system identifies
            the hazards and the specific precautions to be taken to
            control the risks. The PTW system only allows work to begin
            after safe procedures have been defined and satisfied.

            The PTW system forms part of an overall SSoW framework
            and will be introduced for all activities where the potential
            risk is high and if risks cannot be eliminated. Comserve will
            operate a PTW system covering the following medium/high
            risk activities: