and the like. We also take the opportunity to further coordinate our construction
                                               activities with your activities.
         Our teams focus is to
                                               Monthly overview
          protect the project                  At the minimum, we prepare monthly reports detailing the following:
                                               • Project status
              GMP budgets                      • Financial status report
                                               • Cash fl ow report
            and contingency                    • Updated schedule (provided weekly or daily if required)
                                               • Production log
                                               • Safety report
           to be an eff ective                 • Progress photos
                                               • Sustainability/LEED status if required
               construction                    • MBE/WBE/LBE and residency requirements status if required
                                                       • Inspection log
             partner to your                           • Manpower/Superintendent reports
                                                       • Request for Information log
                     team.                             • Change order log
                                                       • Shop drawing log
                                                       • Meeting minutes

                                               Barr & Barr utilizes Prolog Manager construction management software on all of our
                                               projects.  All the fi nancial and cost reporting information is maintained within a secure
                                               environment accessed only by select project team members who have been assigned
                                               a secure username and password.  Th  e Prolog reports are set up to align the budget
                                               codes with the GMP estimate and bid packages to show the process of managing the
                                               project costs with the budgets established in the GMP.

                                               We understand that the budget is a critical element for your project.  Th  is cost and
                                               budget reports are included in each monthly report and will be updated regularly to
                                               be discussed at the Project Meetings.  Our teams focus is to protect the Project GMP
                                               budgets and contingency to be an eff ective construction partner to your team.

                                               7. Site Logistics Plan
                                               Barr & Barr’s main focus on every project within an active academic campus is to
                                               isolate construction and minimize the impact to student, faculty, staff , visitors and
                                               campus operations. Th  is along with our in-depth knowledge of Roosevelt Island and
                                               the Cornell Tech Campus, creates an eff ective streamlined process that benefi ts in
                                               effi  ciency and productivity while maintaining a safe environment.

                                               Given the location of the VEEC on campus logistical planning is paramount.  Following
                                               this section is our preliminary project logistic plans that showcase how we provide
                                               logistical strategy layouts to the owner for review and comment. Th  e impacts we impose
                                               on the campus must be reviewed with Cornell Tech project management prior to any
                                               construction commencing.

                                               Site Boundary and Fencing
                                               Barr & Barr participated in a DOB BEST Squad – Major Project Kickoff  Meeting
                                               5/11/207 to present the Site Logistics for the VEEC with particular focus given to the
                                               immediate adjacency of the Graduate Hotel Project and their simultaneous schedules.
                                               Topics discussed:

                                               1) Access Agreements
                                                       a.  Mutual access agreements is a must for the success of both projects.
                                                       b.  Access agreements should contain language that each project shall allow
                                                         the other good faith access to provide protection required by chapter 33
                                                         building code.
                                                       c.  Th  e access agreements shall be made between the property owners.
                                                       d.  Without access agreements in place the project causing the risk to the other
                                                         must get a court order to protect, initiated by a 60-0day, 45-day and 30-day
                                                         notice to the property owner of the property requiring protection.
                                                       e.  Access Agreements should extend to the CUP building and the Tech Wall.