                              20) Run the airlines through the half section of nylon protective sleeve for each leg. Refer to
                                 the images below for more detail.

                              Note:  Make sure that the nylon protective sleeve is positioned so that it is not allowing the airlines
                                     to rub any of the edges at the slotted area of the filler strip.












                                                    Position the
                                                    sleeves here to         Position the
                                                    prevent the            sleeves here
                                                    airlines from            to prevent
                                                    rubbing against          the airlines
                                                    the filler strip.      from rubbing
                                                                             against the
                                                                             filler strip.

                                 .
                              21) Push the 3/8” airline that is coming from the main air feed union tee to the elbow that is
                                 on the bottom of the side spray manifolds.
                              Note:  Route the airline to the elbow so that it is making a smooth transition from the point it
                                     comes out of the filler strip to the connection point on the elbow.
                              22) Push the 3/8” airline that is coming from the main water/chemical feed union tee to the
                                 elbow that is on the top of the side spray manifolds.

                              Note:  Route the airline to the elbow so that it is making a smooth transition from the point it
                                     comes out of the filler strip to the connection point on the elbow.
                                 At this point everything has been installed on the Arch.
                              23) Turn on the main water and run it through the lines. Check to make sure that there are no
                                 leaks at any point on the system.